Construction is moving at a rapid pace to reach the goal of our Grand Opening in August of 2001. You can follow along with the progress through our weekly updates. Be sure to check back every week to see how we are moving along.

Week 1 (July 3-7)
Demolition begins on July 5. Upper-level bleachers begin to be stripped. By July 7th, the west half of the bleachers are removed.

Week 2 (July 10-14)
Orange spray-paint marks all parts of the building that is to be removed. The upper-level of bleachers, the balcony connecting the blachers, and the four staircases leading up to the top level are all demolished, leaving only the frame and support beams.

Week 3 (July 17-21)
The stage on the north end of the guym is almost demolished and the support beams from the upper-level bleachers begin to be torn down. Walls are removed in the meeting rooms on each corner of the main floor. Repairs begin on the large cracks in the main brick walls. All fixtures from the bathrooms and internal doors are removed. Work begins in the basement, including tearing the bleachers out from the former dance studio. On the west side of the building grounds, the foundation is dug for the restaraunt patio.

QTVR Tour | Features | Location on Campus | Design Sketches


If you have any questions or concerns about the Hansen Student Center or this website, please contact us by e-mail at hansen@titan.iwu.edu